HDR | Andrew Reid is delighted to be involved with the Global Switch North project for T Clarke.
Commissioning Manager role. The scope of the works is to remove existing CRAH units and re-install new ones throughout their Data Centre in London. There are 63 CRAH units over 3 floors.